Dufferin Mall

Dufferin Mall

, ,

Dufferin Mall Pedestrian Tunnel This renovation project includes the challenge of constructing a 10ft wide by 12ft deep pedestrian tunnel inside an active mall. HCM together with RWH Engineering proposed an innovative design and construction process to accomplish this endeavor with very limited working space and tricky access issues. The construction involves: • Shotcrete shoring

Weston Tunnel Grade Separation

Weston Tunnel Grade Separation

Weston Tunnel Grade Separation HC Matcon achieved a significant milestone on the Weston Tunnel project, allowing for the GC to accelerate the schedule and make up for project delays. HCM mobilized 5 large diameter drill rigs and in seven and a half weeks installed 311 soldier piles (12,000 linear feet) drilled into bedrock up to