Weston Tunnel Grade Separation

Weston Tunnel Grade Separation

Weston Tunnel Grade Separation HC Matcon achieved a significant milestone on the Weston Tunnel project, allowing for the GC to accelerate the schedule and make up for project delays. HCM mobilized 5 large diameter drill rigs and in seven and a half weeks installed 311 soldier piles (12,000 linear feet) drilled into bedrock up to